EM - June/July 2014 - (Page 12)
12
12
June/July
GENERATION2014WHOLESALE MARKETS
& * www.esb.ie/em
June/July 2014 * www.esb.ie/em
Generation & Wholesale Markets
Happy 40th Anniversary Turlough Hill!
iversary of
This month marks the 40th ann
pumped
operations starting at Ireland's only
h Hill. On
storage system - ESB Turloug
t to say
behalf of everyone at ESB, I wan
colleagues
congratulations and thank you to
ent involved in building,
both past and pres
ion. It's
operating and maintaining the stat
strong tradition
part of our history and the
ESB, and
of sustainable innovation at
ination and
it's an incredible feat of imag
tinued to
engineering. Turlough Hill has con
ing sure
play a strong role ever since in mak
ents, day in
we meet our customers' requirem
and day out.
Here's to the next 40 years!
Kind regards,
Paddy Hayes
Executive Director Generation
& Wholesale Markets.
SINCE IT'S THE 40th anniversary of
ESB Turlough Hill, it seems like a good
time to flash back and celebrate how it
came to be...
ELECTRICITY FOR AN
EXPANDING ECONOMY
By the late 1960s, ESB had been steadily supplying electricity to customers for
over 40 years. At that point, we knew
that electricity demand would continue
growing across Ireland. We knew we
needed to be responsive and flexible
to help manage that demand. And we
knew we wanted to be as environmentally conscious as possible in whatever
we developed next for existing and future generations.
Designing and developing a pumpedstorage hydro station was a unique and
innovative civil engineering solution
for Ireland at the time - expanding the
electricity supply for a growing population through an environmentallyfriendly system.
Plus, it would provide flexibility
when it came to handling peaks and
troughs in demand throughout any
given day, which is always a challenge.
You can't store electricity for very long
and large power stations can take hours
to fire up before they are working at full
capacity.
Pumped storage, however, can go
from standstill to full capacity/generation in around 70 seconds.
Having a rapidly responsive resource
like this as part of the generation mix
would be a huge advantage to customers across Ireland at peak electricity demand times.
The Hydro Control Centre today at Turlough Hill.
Excavation work being carried out on the massive engineering project which commenced in 1968.
DID YOU KNOW?
'Turlough' is the Gaelic name for a
dry lake - one which loses its water through a swallow hole in dry
weather.
GETTING STARTED
Our engineers started looking for the
right location in County Wicklow, which
features plenty of mountains and lakes,
plus it's also fairly close to one of Ireland's main centres of demand - Dublin.
Eventually, the team settled on Turlough
Hill because it already had a natural corrie lake - Lough Nahagahan - which
could become the lower reservoir for the
station. There was also a suitable site on
the mountain where we could build an
artificial upper reservoir.
DID YOU KNOW?
Turlough Hill is located 60km
south of Dublin in the Wicklow
Mountains close to Glendalough
which is the second most visited
tourist site in Ireland.
With the site decided and with approval from the Government, we
started work on the construction phase
in the autumn of 1970, supported by
many staff from different areas of expertise across ESB, as well as contractors, to bring the project to life.
DIGGING IN
If you take a look at the diagram below, you'll see why the project really
caught the public's imagination at the
time - it was the country's first (and, so
The first unit went live in 1973. The remaining three have been operating since 1974.
far, only) pumped storage station and
there hadn't been anything quite like
it in terms of scale since the Shannon
Scheme was built in the 1920s.
TAKING CARE
ESB was always very conscious that we
were working in an area of outstanding natural beauty and wanted to make
sure we minimised our impact wherever possible. As mentioned earlier, the
main station was buried out of sight,
inside the mountain, but ESB also:
* successfully used a pioneering (at
the time) technique to restore grass
growth on the verges of the newlyconstructed two-mile long road to
the mountain top, using a mix of water, fertiliser, wood pulp, peat moss
and grass seed;
* used the 1.305 million cubic metres
of granite excavated from the upper reservoir to build its embank-
1.
2.
3.
4.
5.
6.
7.
Pump Turbine
Motor/Generator
Main Unit Tranformer
Flap Gate
Turbine Inlet Valve
Pony Motor/Generator
10 kV Switchgear, Control Panels and
Relays.
8. 2 x 70 ton Bridge Cranes
9. False Roof with Soundproofing
10. Haunch Beams
11. 50 ton Bridge Crane
12. Cable Gallery for 220 kV Cables
ment (maximum height: 34m, length:
1,445m);
* made sure that the administration offices and transformer compound can't
be seen from the Wicklow Gap road.
ALL SYSTEMS GO!
In December 1973, ESB Turlough Hill's
first generating unit started operating,
followed by the three other units in the
summer of 1974. And this incredible feat
of civil engineering has been supplying
Ireland with electricity ever since.
In 2004, ESB Turlough Hill became
the Hydro Control Centre (HCC) for
the company. This means that we can
operate any of our 10 hydro stations
direct from one single control room on
site - increasing our responsiveness to
customer needs even further. n
The construction team worked
hard over six years:
* carving out a massive underground chamber inside the
granite mountain to house the
main station, so that it would be
hidden from view (length 82m,
breadth 23m, heigh 28m - the
same space as a medium-sized
cathedral);
* excavating 2.5 million tonnes of
rock to build the upper lake, then
lining it with asphaltic concrete;
* drilling tunnels through the rock
to connect the station and the upper/lower lakes.
Table of Contents for the Digital Edition of EM - June/July 2014
EM - June/July 2014
Contents
News
Innovation
Generation & Wholesale Markets
BSC & Electric Ireland
ESB Network Ltd
Health & Habitat
EM - June/July 2014
http://europe.nxtbook.com/nxteu/zahra/em_20150203
http://europe.nxtbook.com/nxteu/zahra/em_20151201
http://europe.nxtbook.com/nxteu/zahra/em_20141011
http://europe.nxtbook.com/nxteu/zahra/em_20140809
http://europe.nxtbook.com/nxteu/zahra/em_20140607
http://europe.nxtbook.com/nxteu/zahra/em_20140405
http://europe.nxtbook.com/nxteu/zahra/em_stormspecial
http://europe.nxtbook.com/nxteu/zahra/em_esbenergy
http://europe.nxtbook.com/nxteu/zahra/em_20140203
http://europe.nxtbook.com/nxteu/zahra/em_20141201
http://europe.nxtbook.com/nxteu/zahra/em_20131011
http://europe.nxtbook.com/nxteu/zahra/em_20130809
http://europe.nxtbook.com/nxteu/zahra/em_20130607
http://europe.nxtbook.com/nxteu/zahra/em_20130405
http://europe.nxtbook.com/nxteu/zahra/em_20130203
http://europe.nxtbook.com/nxteu/zahra/em_20131201
http://europe.nxtbook.com/nxteu/zahra/em_20121011
http://europe.nxtbook.com/nxteu/zahra/em_20120809
http://europe.nxtbook.com/nxteu/zahra/em_20120607
http://europe.nxtbook.com/nxteu/zahra/em_20120405
http://europe.nxtbook.com/nxteu/zahra/em_20120203
http://europe.nxtbook.com/nxteu/zahra/em_20111201
http://europe.nxtbook.com/nxteu/zahra/sa_2011
http://europe.nxtbook.com/nxteu/zahra/em_20111011
http://europe.nxtbook.com/nxteu/zahra/em_20110809
http://europe.nxtbook.com/nxteu/zahra/em_20110607
http://europe.nxtbook.com/nxteu/zahra/em_20110405
http://europe.nxtbook.com/nxteu/zahra/em_20110203
http://europe.nxtbook.com/nxteu/zahra/em_20101201
http://europe.nxtbook.com/nxteu/zahra/em_20101011
http://europe.nxtbook.com/nxteu/zahra/em_20100809
https://www.nxtbook.com/nxteu/zahra/em_20100607
https://www.nxtbookmedia.com