EM - October/November 2013 - (Page 22)
22
October/November 2013 www.esb.ie/em
April/May 2013 • www.esb.ie/em
ESB Networks Ltd
GATE 3 WIND FARM PROJECTS
The Gate System
THE CONNECTION of renewable
energy to the electricity network is
managed in Ireland by the application
of the Group Processing Approach
(GPA). This is effectively an open bidding process, whereby tranches of applicants are processed in blocks, such
as the Southwest hub. These blocks
are known as Gates and to date there
have been three gates: Gates 1, 2 and
3. Gates 1 and 2 are being built at the
moment and total 2,500MW.
These issues have both been resolved by CER and the Department
of Communications Energy and
Natural Resources. EirGrid have carried out their studies to produce constraint reports, i.e., to study the impact of these projects on the system.
Each Gate 3 applicant is
given 11 weeks to accept
their offer, or otherwise
the offer lapses. By the end
of September, the expiry
date will have passed for
120 applicants seeking to
connect to the Distribution Network and 30 applicants seeking connection to the
Transmission Network. It is anticipated that there will be almost 100%
acceptances of offers.
It is not expected that all of the
applicants will seek immediate connection. There are a number of other
conditions a developer must meet to
get Finance to build and proceed to
construction, including:
• Planning permission
• Environmental requirements –
SACs, etc. (Special Areas of Conservation).
• Sites, site access, Wayleaves and
Consent.
It is anticipated, however, that a significant
proportion will progress to construction.
This constitutes a major block of work and
will place substantial
demands on the Renewable Energy Teams
in Asset Management
and HVD&C to ensure
the prompt delivery of
connections. These connections will require the
delivery of new and the extension of
existing 110kV and 38kV substations
and the construction and installation
of large volumes of 38kV and MV
OH lines and UG Cables. The impact
of these connections is further complicated by the fact that developers
can opt to build the major portion of
the works contestably, that is, using
their own design and build teams. n
Gate 3 is, in total, a further
4,500MW, with potentially 30
Grid connected projects and 120
projects connected to the Distribution system. Gate 3 offers
have been issued and developers
must now decide whether to accept or not. Some of these offers
were issued over two years ago,
but could not be accepted up to
now as developers did not have
certainty on:
• The level of Dispatch, i.e., as
there would potentially be
more capacity available than
needed at times, those who
built out first were being given
priority. This made newer projects potentially unviable. This
is now being done on a pro rata
basis for all.
• Time limits set for Refit 2 has
been extended from 2015 to
2017.
The total installed capacity nationally is now at 1,790MW
(1,023MW Distribution and
767MW Grid)
There was a peak Generation
of 1,540MW on March 21st last.
There are some 70 projects at design and construct stage. By yearend with a potential additional
capacity of 490MW will be connected 2013, taking the Republic
of Ireland over the 2GW mark in
terms of installed capacity.
ESB Networks
goes for gold!
Page 24
ESB NETWORKS KICKS-OFF MAJOR
PAN-EUROPEAN COLLABORATIVE
PROJECT – EVOLVDSO
INCREASING RENEWABLES penetrations across Europe are demanding
that the DSO takes on new roles and
responsibilities. EvolveDSO is a major EU FP7-funded project which will
clearly define these new roles. The project will identify, develop and test the
tools which DSOs will need to effectively evolve into and fulfil these roles.
The wide array of distributed energy resources connected at MV&LV,
the convergence of electricity and telecoms infrastructures and the emergence of distributed storage and demand response are driving changes
in the way DSOs plan and operate
their networks. New approaches and
tools for distribution planning, operations, scheduling and maintenance
will be developed and tested under
evolvDSO. This will contribute to the
transition to a more sustainable European energy system by maintaining and increasing the security and
reliability of distribution grids while
facilitating the increased feed-in of
distributed renewable generation.
evolvDSO is a realisation of the EEGI
roadmap and ultimately provides a
significant impetus for reaching EU
climate targets. n
The project consortium consists
of 16 partners, joining 12 of the
most progressive European
DSOs with TSOs and academia
across eight countries. This is
a €7.9m collaborative project
with €5.3m being provided
directly by the EU under FP7.
The project has a 40 month
duration and officially commenced in September.
Pictured making a presentation to Christy and his wife Nellie are Executive Director ESB Networks
Ltd, Jerry O’Sullivan, and Denise Fannin, ESB Networks.
CHRISTY KING RETIRES
ON THURSDAY AUGUST 29TH we
joined with Christy King as he celebrated 43 years in ESB and moved
on to retirement. Jerry O’Sullivan,
MD ESB Network Ltd, welcomed
Christy’s wife, Nellie, his children,
Mark, Carol, Anne and Christopher,
his brothers and sisters, neighbours,
colleagues, union officials and many
friends to a very large gathering at
the Goat Grill in Dublin.
Christy’s approach to his role in
Industrial Relations is to build good
working relationships with all union leaders and to be true to his
core belief that “it’s all about trust”.
Throughout his career, he has continued to find time to deal with
personal issues, where his humanity and compassion earned him the
respect of a wide range of people
across ESB. Christy is a proud Wicklow man. He grew up and still lives
at the foot of the Sugarloaf mountain in Kilmacanogue. He joined
ESB in 1970 in the Payroll Unit of
Dublin South District and became
Payroll Unit Head in 1979. In 1985
he became Staff Services Officer
(EAP), where he began to find his
true home looking after people and
the issues that affect them. After a
number of years in that role he became involved in general Human
Resources and Industrial Relations
work, including the implementation
of Partnership in Dublin Region. In
1999 he moved to a role in IR in ESB
Networks and was appointed as Employee Relations Manager in 2003.
Paying tribute to Christy, Jerry O’Sullivan said: “Christy has
touched the lives of many people in a
caring and supportive way. He does
things because it is the right thing
to do! He has made deep and lasting friendships with many people in
ESB.” As Christy often said: “We are
all in this together!”
We wish Christy, Nellie and their
family every success and continued
health and happiness in the future. n
http://www.esb.ie/em
Table of Contents for the Digital Edition of EM - October/November 2013
EM - October/November 2013
Contents
News
Innovation
Generation & Wholesale Markets
BSC & Electric Ireland
ESB Networks Ltd
Health & Habitat
EM - October/November 2013
http://europe.nxtbook.com/nxteu/zahra/em_20150203
http://europe.nxtbook.com/nxteu/zahra/em_20151201
http://europe.nxtbook.com/nxteu/zahra/em_20141011
http://europe.nxtbook.com/nxteu/zahra/em_20140809
http://europe.nxtbook.com/nxteu/zahra/em_20140607
http://europe.nxtbook.com/nxteu/zahra/em_20140405
http://europe.nxtbook.com/nxteu/zahra/em_stormspecial
http://europe.nxtbook.com/nxteu/zahra/em_esbenergy
http://europe.nxtbook.com/nxteu/zahra/em_20140203
http://europe.nxtbook.com/nxteu/zahra/em_20141201
http://europe.nxtbook.com/nxteu/zahra/em_20131011
http://europe.nxtbook.com/nxteu/zahra/em_20130809
http://europe.nxtbook.com/nxteu/zahra/em_20130607
http://europe.nxtbook.com/nxteu/zahra/em_20130405
http://europe.nxtbook.com/nxteu/zahra/em_20130203
http://europe.nxtbook.com/nxteu/zahra/em_20131201
http://europe.nxtbook.com/nxteu/zahra/em_20121011
http://europe.nxtbook.com/nxteu/zahra/em_20120809
http://europe.nxtbook.com/nxteu/zahra/em_20120607
http://europe.nxtbook.com/nxteu/zahra/em_20120405
http://europe.nxtbook.com/nxteu/zahra/em_20120203
http://europe.nxtbook.com/nxteu/zahra/em_20111201
http://europe.nxtbook.com/nxteu/zahra/sa_2011
http://europe.nxtbook.com/nxteu/zahra/em_20111011
http://europe.nxtbook.com/nxteu/zahra/em_20110809
http://europe.nxtbook.com/nxteu/zahra/em_20110607
http://europe.nxtbook.com/nxteu/zahra/em_20110405
http://europe.nxtbook.com/nxteu/zahra/em_20110203
http://europe.nxtbook.com/nxteu/zahra/em_20101201
http://europe.nxtbook.com/nxteu/zahra/em_20101011
http://europe.nxtbook.com/nxteu/zahra/em_20100809
https://www.nxtbook.com/nxteu/zahra/em_20100607
https://www.nxtbookmedia.com